Sprint Capacity & Velocity Forecast Calculator

Work out your team's capacity for the next sprint and forecast how many sprints the remaining backlog will take, using your recent velocity.

1 · Team capacity for the next sprint

Team memberDays availableHours per dayFocus %Hours

2 · Velocity and backlog

Team capacity hHours of focused work this sprint
Average velocity ptsRange –
Sprints needed (average)≈ weeks
Best / worst case / Using your highest and lowest velocity

How sprint capacity and velocity forecasting work

Capacity is the time the team can actually spend on sprint work. It is days available × hours per day × a focus factor, which covers meetings, support and interruptions. Most teams use 60–80% focus. Use capacity in sprint planning to avoid over-committing.

Capacity (hours) = Σ days available × hours per day × focus %
Sprints needed = remaining backlog ÷ average velocity (rounded up)

Velocity is the number of story points the team completes per sprint. Forecasting with a range (best, average and worst velocity) is more honest than a single date, and it matches how agile teams communicate release plans.

Worked example

A team with velocities of 28, 32 and 30 averages 30 points. A 240-point backlog needs 8 sprints on average, and 8 to 9 sprints across the best and worst cases. With two-week sprints, that is about 16 to 18 weeks.

Tips

  • Use at least three recent sprints. Velocity from a new or changing team is unreliable.
  • Velocity is for planning, not for comparing teams. Points are relative to each team.
  • Add to the backlog estimate when scope grows. A burnup chart makes this visible.

Related: velocity, story points, sprint planning, burndown chart.