Estimate at Completion (EAC)
The expected total cost of completing all work. A common formula is EAC = BAC ÷ CPI when current cost performance is expected to continue.
Example
With BAC $250,000 and CPI 0.934 (170,000 ÷ 182,000), EAC ≈ $267,650.