Five free full-length risk management practice exams: 115 questions in 150 minutes each, with EMV, PERT and Monte Carlo questions and results by domain.

What the exam covers

PMI-RMP exam overview and study plan

Sample PMI-RMP practice questions

These 6 questions come from the first PMI-RMP mock exam. The simulator has the full exams, with a timer and results by domain.

Question 1 (Risk Strategy and Planning)

You have just been assigned as risk manager on a new infrastructure program. What should you do first to understand the risk context?

  1. Review the business case, charter, contracts and lessons learned from similar programs
  2. Hold a risk identification workshop with the full team to build the register quickly
  3. Ask the sponsor to approve a contingency reserve of 10% of the program budget
  4. Run a Monte Carlo simulation on the draft schedule to find the likely finish date

Answer: A. A preliminary document analysis comes first. The business case, charter, contracts and lessons learned show objectives, constraints and known risk sources before any workshop is run.

Question 2 (Risk Identification)

What is the main purpose of a risk identification workshop?

  1. To find as many relevant uncertain events and conditions as possible, from many viewpoints
  2. To agree responses and owners for the top ten risks that the sponsor is worried about
  3. To estimate the probability and impact of every risk on the current register
  4. To confirm that the contingency reserve is large enough to cover all known risks

Answer: A. Identification aims for breadth: finding risks from many perspectives. Analysis and response planning come later.

Question 3 (Risk Analysis)

What is the main purpose of qualitative risk analysis?

  1. To prioritize individual risks for further action by assessing probability, impact and other characteristics
  2. To calculate the overall probability of meeting the project's cost and schedule objectives
  3. To identify every risk that might affect the project before planning begins
  4. To decide the risk response for each risk and assign action owners

Answer: A. Qualitative analysis prioritizes individual risks, usually by probability and impact, so the team focuses on the most important ones.

Question 4 (Risk Response)

A team changes the design to remove a component that has a history of failures. Which threat response is this?

  1. Avoid
  2. Mitigate
  3. Transfer
  4. Accept

Answer: A. Changing the plan so that the threat can no longer occur, or has no effect, is avoidance.

Question 5 (Monitor and Close Risks)

Which data best shows whether risk responses are working?

  1. Changes in risk scores and exposure after responses are implemented
  2. The number of risks added to the register each month
  3. The number of attendees at each risk review
  4. The length of the risk register

Answer: A. The effect of responses is seen in changes to probability, impact and overall exposure.

Question 6 (Risk Strategy and Planning)

During an environmental scan, the team finds that a key supplier is about to launch a faster component. How should this be treated?

  1. As a possible opportunity to assess and plan for
  2. As an issue to log and escalate immediately
  3. As a constraint that limits the design options
  4. As an assumption to remove from the scope

Answer: A. An uncertain event with a positive effect on objectives is an opportunity. It should be identified, assessed and planned like a threat.