Cost · PM Glossary

To-Complete Performance Index (TCPI)

The cost performance needed on the remaining work to meet a target: TCPI = (BAC − EV) ÷ (BAC − AC).

Example

TCPI = (250,000 − 170,000) ÷ (250,000 − 182,000) = 1.18, which is hard to achieve.